Works / Energy / Transmission Lines

CEA – COMPLEXO CAPOEIRAS & ASSURUÁ 235 MW

Objeto

Design and execution of civil and electromechanical works for the implementation of the 235 MW Assuruá Project, including engineering services (basic and executive projects), execution of main and secondary access roads, platforms, bases and foundations, reinforced concrete structure, works earthworks, drainage and QSMS, including the supply of equipment, materials, complementary tests, material management and labor management for Centrais Eólicas Assuruá SA

Location

Xique Xique and Gentio do Ouro / Bahia / Brazil

Technical information

Power: 235 MW - 15 AEG Gamesa of 2 MW HH 80 M and 82 AEG GE 2.5 MW HH 80 M
Transmission Lines: 138 Kv
Simple circuit: 9.45 km
Medium Voltage Network: 77.9 km - Aerial 34.5 KV

Develop your project with quality.

TOP
Folders GEL