Contractor
EDP Renováveis
Objeto
BOP Civil and RMT Execution of bases for 21 5.9 MW wind turbines.
Location
Pocinhos / PB / Brasil
Deadline
Dec/23 to May/25
Technical information
Earth moved: 490,200 m³;
Installed power: 123.9 MW.
EDP Renováveis
BOP Civil and RMT Execution of bases for 21 5.9 MW wind turbines.
Pocinhos / PB / Brasil
Dec/23 to May/25
Earth moved: 490,200 m³;
Installed power: 123.9 MW.