Works / Infrastructure

PCH CONFLUÊNCIA

Objeto

EXECUTION OF THE CONSTRUCTION SERVICES FOR A SHP (SMALL HYDROELECTRIC POWER PLANT) LOCATED AT THE CONFLUENCE OF THE MARRECADAS AND CACHOEIRINHA RIVERS. PRUDENTÓPOLIS E TURVO/PR – INSTALLED POWER – 82.800 KW

Location

Turvo / Paraná / Brazil

Deadline

Mar/2021 to Dec/2022

Technical information

MAIN QUANTITATIVES:
EXCAVATION 1,229,010 m³
LANDFILE 293,728 m³
ROCKFILL 33,055 m³
CCV CONCRETE 33,746 m³
CCR CONCRETE 30,050 m³
TUNNEL SECTION 4.50 X 4.50 - 970 m
ADDUCTION CHANNEL 2,880 m

CONTRACT VALUE
US$ 33 million

WORKFORCE
420 (22 upper level)