Objeto
Execution of the construction works for wind turbine bases, including grounding, foundations, earthworks and paving of the Complexo Eólico Gameleiras for CPFL Energia Renováveis SA
Location
Touros / Rio Grande do Norte / Brazil
Technical information
SPE COSTA DAS DUNAS ENERGIA S.A.
Earthwork: 64,547 m³
Reinforced concrete: 2.855 m³
Pile driven: 2,434 m
Buildings: 540 m²
As Built grounding system - electrical installation: 8 units
Drainage: 4,501 m
Beam and foundation: 2 units
Excavation: 8,412 m³
Earth movement - cut: 109,274 m³
SPE GAMELEIRA ENERGIA S.A.
Earthwork: 27,663 m³
Reinforced concrete: 1,784 m³
Pile driven: 2,028 m
As Built grounding system - electrical installation: 5 units
Drainage: 1,929 m
Excavation: 5,257 m³
Earth movement - cut: 46,831 m³
SPE FAROL DE TOUROS ENERGIA S.A.
Earthwork: 55,326 m³
Reinforced concrete: 2.498 m³
Pile driven: 2,840 m
As Built grounding system - electrical installation: 7 units
Drainage: 3,858, m
Excavation: 7,360 m³
Earth movement - cut: 93,663 m³
SPE FIGUEIRA BRANCA ENERGIA S.A
Earthwork: 36,884 m³
Reinforced concrete: 1,070 m³
Pile driven: 1,217 m
As Built grounding system - electrical installation: 3 units
Drainage: 2,572 m
Excavation: 3,154 m³
Earth movement - cut: 62.442 m³